CSR Factory Relocation

Under the direction of CSR, Lucan Engineering was involved in the decommissioning and relocation of an insulation manufacturing and production line in Wetherill Park. The process involved:

  • Electrical and pneumatic disconnection.
  • Decommissioning and tag out of machinery.
  • Pulldown of structural platforms and supports.
  • Digital mapping of existing factory layout to ensure relocation ran smoothly.
  • Conducting lifts with the use of two 20t Frannas and 3.5t forklifts.
  • Providing transportation to new factory in Villawood.

Location

CSR Process & Manufacture Facility located in Wetherill Park

Client

CSR

Completion

04 / 2021