Waste Compaction System Replacement Project at Veolia Clyde Transfer Station

  • Project management.
  • Design drafting.
  • Mechanical and electrical installation services to carryout the scope of works required.
  • Install new Compactor in pit ready for commissioning.
  • Manufacture and install a new rail and trolley moving mechanism.
  • Resurface and re establish bunded area, including water proofing and grouting in and around newly installed Compactor.

Location

319 Great Western Hwy, Auburn 2144

Client

Clarke Energy

Date of Completion

04 / 2017